2018 CONSTRUCTION PROJECTS


County Road 4 & 26 Reconstruction  

Location:  CR 4 from US Hwy 12 to CR 10 - MAP    Future Trail Location
Contractor:  Central Specialties, Inc.
Approx. Start:   July 23, 2018
Approx. Finish:   August 2019
Description:  This project consists of grading, aggregate base, curb/gutter, storm sewer and county park improvements.
Detour:  MAP

County Park Access
September 14th update:  

Central Specialties have the southern most mile of CSAH 4 graded and are currently placing aggregate.  They are continuing to dry the grade between 38th Ave NE and 49th Ave NE with the hopes of placing aggregate there soon.  The mill is currently salvaging aggregate along the southwest shore of Diamond Lake in anticipation of grading operations beginning there as well.  Scrapers and dozers continue to work on the road grade in the new location areas of CR 26 and behind the county park along with installing storm sewer in these areas.

Work continues in the county park as the infiltration basin is almost complete now.  The road has been removed in front of the park area and storm sewer continues to be installed ahead of the parking lot construction.

The county park and CR 28 are accessible from the north only.  Please see the County Park Access map above.



County Road 5 Reconstruction


Location:  CR 5 from CR 40 to TH 9 - MAP
Contractor:   R and G Construction Co. - ICON Constructors (Bridge)
Approx. Start:   February 26, 2018
Approx. Finish:   August 2018
Description:  This project consists of grading, aggregate base and new bridge at Games Lake outlet.
Detour:  MAP
August 30th update:  

Project is complete.


2018 Bituminous Surfacing 

Location:  Kandiyohi County - MAP
Contractor:   Duininick, Inc.
Approx. Start:   May 2018
Approx. Finish:   August 2018
Description:  This project consists of new bituminous surfacing and bituminous overlays located throughout Kandiyohi County.
Detour:  There are no detours associated with this project.  Work will be done under traffic.

August 15th update: 
This contract is now complete.


County Road 5 Trail  

Location:  Along CR 5 from 189th Ave NW to TH 9 - MAP
Contractor:   Duininick, Inc.
Approx. Start:   August 2018
Approx. Finish:   September 2018
Description:  This project consists of a new bituminous trail adjacent to CR 5.
Detour:  There are no detours associated with this project.  Work will be done under traffic.

September 14th update: 
The trail is now paved and Northstar Landscaping are beginning to prep the disturbed areas for seeding.  There are a few areas of the trail that will need to modified yet.