KANDIYOHI COUNTY CONSTRUCTION PROJECTS

2021 program



#1 - CR 4 Reconstruction (034-604-030)
Location:   CR 4 from CR 83 to north of CR 20
Contractor:   Minnerath Construction of Cold Spring, MN
Approx. Start:   June 7, 2021
Approx. Finish:   October 2021
Description:   This project consists of the reconstruction of CR 4 from CR 83 to north of CR 20
Detour:   MAP
Update:  7/20/2021:  Minnerath is beginning to wrap up the south phase by starting to place gravel surfacing on the project.  Beginning on Wednesday, the detour will be adjusted to include the entire stretch of CR 4.  Milling operations will begin on Phase 2 of the project.


#2 - CR 44 Reconstruction (034-644-008)
Location:   CR 44 from TH 7 to 150th Ave SE
Contractor:   Riley Bros. Construction of Morris, MN
Approx. Start:   June 1, 2021
Approx. Finish:   
Description:   This project consists of grading and aggregate base on CR 44 from TH 7 to 150th Ave SE
Detour:   MAP
Update: 7/21/2021:  Riley Bros. continue to grade the new road from CR 16 to 150th Ave SE.  Gravel surfacing is currently being place on the new road from TH 7 to CR 16.


#3 - CR 1 Reconstruction (034-601-037)
Location:   CR 1 from TH 7 to north city limits of Prinsburg
Contractor:   Duininck, Inc. of Prinsburg, MN
Approx. Start:   July 6, 2021
Approx. Finish:   October 1, 2021
Description:   This project consists of grading and bituminous surfacing on CR 1 from TH 7 to north city limits
Detour:   MAP
Update:  7/21/2021:  Duininck continues to install new storm sewer on the project.  This operation will continue for a few weeks.


#4 - CR 8 Bituminous Overlay (034-608-027)
Location:   CR 8 from Kandiyohi to CR 10
Contractor:   Duininck, Inc. of Prinsburg, MN
Approx. Start:   May 17, 2021
Approx. Finish:   June 11, 2021
Description:   This project consists of milling and bituminous overlay on CR 8 from Kandiyohi to CR 10
Detour:   None.  This project will be constructed under traffic.  Drive slow through construction operations and follow signs and flaggers.  
Update:  7/21/2021:  The project is now complete.  Waiting for grooved in fog line striping from another contract.


#5 - CR 40 Bituminous Surfacing (034-640-020)
Location:   CR 40 from CR 4 to CR 2
Contractor:   Central Specialties Inc. of Alexandria, MN
Approx. Start:   May 3, 2021
Approx. Finish:   May 14, 2021
Description:   This project consists of the bituminous surfacing and shouldering of last year's grading project on CR 40 from CR 4 to CR 2
Detour:   None.  This project will be constructed under traffic.  Drive slow through construction operations and follow signs and flaggers.  
Update:  6/15/2021:  Project is now complete


#6 - CR 8 Bituminous Surfacing (034-608-029)
Location:   CR 8 in Lake Lillian
Contractor:   Central Specialties Inc. of Alexandria, MN
Approx. Start:   August, 2021
Approx. Finish:   August, 2021
Description:   This project consists of the bituminous surfacing and shouldering of last year's grading project on CR 8 in Lake Lillian
Detour:   None.  This project will be constructed under traffic.  Drive slow through construction operations and follow signs and flaggers.  
Update:  7/21/2021:  Landwehr Construction is finishing up required patching and milling this week.  CSI plans to be back in the area starting the second week of August.


#7 - CR 5/15 Bituminous Surfacing (034-615-012)
Location:   CR 5/15 from TH 23 to the roundabout south of Jennie-O
Contractor:   Central Specialties Inc. of Alexandria, MN
Approx. Start:   August, 2021
Approx. Finish:   August, 2021
Description:   This project consists of the bituminous surfacing and shouldering of last year's grading project on CR 15 near TH 23, along with a bituminous overlay of CR 15 from the grading project to the roundabout south of Jennie-O.
Detour:   None.  This project will be constructed under traffic.  Drive slow through construction operations and follow signs and flaggers.  
Update:  5/27/2021:  CSI has patched a few areas on the project.  Paving operations will not begin until closer to August.


#8 - CR 5 Bituminous Overlay (034-605-040)
Location:   CR 5 from the railroad tracks near old TH 12 to CR 24 (college road)
Contractor:   Central Specialties Inc. of Alexandria, MN
Approx. Start:   May 7, 2021
Approx. Finish:   May 14, 2021
Description:   This project consists of a bituminous overlay from the railroad tracks near old TH 12 to CR 24 (college road)
Detour:   None.  This project will be constructed under traffic.  Drive slow through construction operations and follow signs and flaggers.  
Update:  6/15/2021:  This project is now complete.


#9 - CR 10 Bituminous Overlay (034-610-020)
Location:   CR 10 from Charley Arne Road to east of CR 95
Contractor:   Central Specialties Inc. of Alexandria, MN
Approx. Start:   May 3, 2021
Approx. Finish:   May 7, 2021
Description:   This project consists of milling and bituminous overlay on CR 10 from Charley Arne Road to a few hundred feet east of CR 95.  Concrete sidewalk repair is also planned with this project.
Detour:   None.  This project will be constructed under traffic.  Drive slow through construction operations and follow signs and flaggers.  
Update:  6/15/2021:  This project is now complete.


#10 - CR 2 Bituminous Overlay (034-602-039)
Location:   CR 2 from CR 20 to Atwater
Contractor:   Central Specialties Inc. of Alexandria, MN
Approx. Start:   August-September, 2021
Approx. Finish:   August-September, 2021
Description:   This project consists of a bituminous overlay on CR 2 from CR 23 to Atwater
Detour:   None.  This project will be constructed under traffic.  Drive slow through construction operations and follow signs and flaggers.  
Update:  5/6/2021:  CSI has indicated that this work will be done in August.

#11 - CR 2 Bridge Replacement (034-602-037)
Location:   On CR 2 approximately 0.5 miles south of TH 55
Contractor:   Robert R. Schroeder Construction of Glenwood, MN
Approx. Start:   July 15, 2021
Approx. Finish:   November, 2021
Description:   This project consists of a bridge replacement on CR 2 over the North Fork of the Crow River, approximately 0.5 miles south of TH 55
Detour:   MAP
Update:  7/21/2021:  The bridge is now closed to traffic and the contractor has started to remove the old structure.
#12 - CR 16 Culvert Replacement (034-616-002)
Location:   On CR 16 approximately 0.4 miles west of CR 2
Contractor:   Houle Construction of Little Falls, MN
Approx. Start:   July, 2021
Approx. Finish:   July, 2021
Description:   This project consists of a culvert replacement on CR 16 over State Ditch 1 approximately 0.4 miles west of CR 2
Detour:  None.  The road will be closed for a period of 10 days while the culvert is replaced.  Use alternate routes.
Update:  7/21/2021:  Houle Construction will close the road on Monday, July 26th to begin removing the old culvert.

#13 - 6" Wet Reflective/Grooved In Edgeline (034-070-012)
Location:   Various Roads in Kandiyohi County
Contractor:   AAA Striping Service of St. Michael, MN
Approx. Start:   TBD
Approx. Finish:   TBD
Description:   This project consists of applying a 6" wide wet reflective, grooved in edgeline along qualifying roads in Kandiyohi County.
Detour:  None.  All work is done under traffic with either flaggers or warning vehicles.
Update:  7/21/2021:  There is a backorder on striping paint.  The contractor will notify the county when it comes in so they can begin the project.

#14 - Maintenance Crack Filling (CF-21)
Location:   Various Roads in Kandiyohi County
Contractor:   Jet-Black of Willmar of Kandiyohi, MN
Approx. Start:   TBD
Approx. Finish:   TBD
Description:   This project consists of routing and filling cracks along various roads within Kandiyohi County.
Detour:  None.  All work is done under traffic with either flaggers or warning vehicles.
Update:  7/21/2021:  Jet-Black is currently working on CR 15 in the City of Willmar.

#15 - Maintenance Seal Coat (SC-21)
Location:   Various Roads in Kandiyohi County
Contractor:   Pearson Bros. Inc of Hanover, MN
   TBD
Approx. Finish:   TBD
Description:   This project consists of seal coating various roads within Kandiyohi County.
Detour:  None.  All work is done under traffic with either flaggers or warning vehicles.
Update:  6/15/2021:  Pearson Bros. have completed the seal coat routes.