KANDIYOHI COUNTY CONSTRUCTION PROJECTS

2020 Kandiyohi County Construction Program
2020 Kandiyohi County Construction Program-map


#1 - CR 8 Reconstruction (034-608-028)
Location:   CR 8 in Lake Lillian
Contractor:   Landwehr Construction
Approx. Start:   August 2020
Approx. Finish:   June 2021
Description:   This project consists of the reconstruction of CR 8 from TH 7 to CR 4
Detour:   MAP
Update: 10-5-20:  The contractor continues to work on the storm sewer along CSAH 8.  

#2 - CR 5 Reconstruction (034-605-038)
Location:   CR 5 from Bridge 34030 to 0.5 miles north  - MAP   
Contractor:   Hoffman Construction Company of Black River Falls, WI
Approx. Start
 May 2020
Approx. Finish:   September 2020
Description:       This project consists of the realignment of CSAH 5 to better align with future phases                                                                  
Detour:   MAP
Update:        10-5-20:  Gravel surfacing is beginning to be placed on the new road grade.  This work should last a week or so.  Seeding operations will also begin this week.  The current phasing plan for this area can be found here








#3 - CR 40 Reconstruction (034-640-019)
Location:   CR 40 from CR 4 to CR 2 - MAP  
Contractor:   Duininck, Inc.
Approx. Start:   June 2020
Approx. Finish:   October 2020
Description:   This project consists of grading and aggregate base
Detour:   MAP
Update:  9-9-20:  The project has been completed with the exception of some seeding and erosion control items yet to be placed.  The detour is scheduled to come off next week and the road will be open to the public.


#4 - CR 5 Turn Lane Construction (034-605-039)
Location:   CR 5 from 7th St NW to CR 24 (south bound lane only)  MAP
Contractor:   Duininck, Inc.
Approx. Start:   June 2020
Approx. Finish:   August 2020
Description:   This project consists of the construction of multiple turn lanes along CR 5
Detour:   There is no detour for this project.  Work will be done by shifting traffic.
Update: 8-17-20:  This project has been completed and striped.  A thin overlay will be added next year.

#5 - Diamond Lake Trail (034-090-003)
Location:  Along CR 4 from 49th Ave NE to Diamond Lake County Park- MAP   
Contractor:  Duininick, Inc.
Approx. Start:   May 2020
Approx. Finish:   June 2020
Description:  This project consists of bituminous trail construction.                                                                          
Detour:  None.  Off road construction.  Watch for construction vehicles.
Update:  7-1-20:  The trail has been fixed and is now complete.

#6,7,9,10,11,12,13,14,15 (2020 Bituminous Surfacing)
Location:   County Wide - See Project Map above
Contractor:   Central Specialties, Inc.
Approx. Start:   May 2020
Approx. Finish:   September 2020
Description:   This project consists of several bituminous overlays and new pavement on county roads across the county.
Detour:  There are no detours associated with this contract.  All work will be done under traffic.
Update:  10-5-20:  Central Specialties began work around Green Lake last week with the milling of the existing surface on CR 144, CR 131, and CSAH 30.  The started to pave CR 144 this morning and will continue to mill CSAH 30.  


#8 - CR 8 FDR (034-608-026)
Location:   CR 8 from CR 4 to CR 20 - MAP  
Contractor:   Duininck, Inc.
Approx. Start:   August 2019
Approx. Finish:   May 2020
Description:   This project consists of milling, reclamation, bituminous surfacing and Bridges 34J48 & 34J51
Detour:  MAP
Update:  7-31-20:  The project has been completed.


#15 - Mamre Township Bridge (034-599-039)
Location:   On 120th St NW approx. 1.2 miles south of CR 27 - MAP 
Contractor:   Riley Bros. Construction, Inc.
Approx. Start:   May 2020
Approx. Finish:   May 2020
Description:   This project consists of a bridge replacement in Mamre Township
Detour:  There is no detour associated with this project.  The road will be closed, use alternate routes.
Update:  6-19-20:  Project has been completed.