KANDIYOHI COUNTY CONSTRUCTION PROJECTS

2020 Kandiyohi County Construction Program
2020 Kandiyohi County Construction Program-map


#1 - CR 8 Reconstruction (034-608-028)
Location:   CR 8 in Lake Lillian
Contractor:   Landwehr Construction
Approx. Start:   August 2020
Approx. Finish:   June 2021
Description:   This project consists of the reconstruction of CR 8 from TH 7 to CR 4
Detour:   MAP
Update:  

#2 - CR 5 Reconstruction (034-605-038)
Location:   CR 5 from Bridge 34030 to 0.5 miles north  - MAP   
Contractor:   Hoffman Construction Company of Black River Falls, WI
Approx. Start
 May 2020
Approx. Finish:   September 2020
Description:       This project consists of the realignment of CSAH 5 to better align with future phases                                                                  
Detour:   MAP
Update:        11-6-20:  This project is now complete.  Final surfacing will be placed next year.  The current phasing plan for this area can be found here








#3 - CR 40 Reconstruction (034-640-019)
Location:   CR 40 from CR 4 to CR 2 - MAP  
Contractor:   Duininck, Inc.
Approx. Start:   June 2020
Approx. Finish:   October 2020
Description:   This project consists of grading and aggregate base
Detour:   MAP
Update:  11-6-20:  This project is now complete.  Final surfacing will be placed next year.


#4 - CR 5 Turn Lane Construction (034-605-039)
Location:   CR 5 from 7th St NW to CR 24 (south bound lane only)  MAP
Contractor:   Duininck, Inc.
Approx. Start:   June 2020
Approx. Finish:   August 2020
Description:   This project consists of the construction of multiple turn lanes along CR 5
Detour:   There is no detour for this project.  Work will be done by shifting traffic.
Update: 8-17-20:  This project has been completed and striped.  A thin overlay will be added next year.

#5 - Diamond Lake Trail (034-090-003)
Location:  Along CR 4 from 49th Ave NE to Diamond Lake County Park- MAP   
Contractor:  Duininick, Inc.
Approx. Start:   May 2020
Approx. Finish:   June 2020
Description:  This project consists of bituminous trail construction.                                                                          
Detour:  None.  Off road construction.  Watch for construction vehicles.
Update:  7-1-20:  The trail has been fixed and is now complete.

#6,7,9,10,11,12,13,14,15 (2020 Bituminous Surfacing)
Location:   County Wide - See Project Map above
Contractor:   Central Specialties, Inc.
Approx. Start:   May 2020
Approx. Finish:   September 2020
Description:   This project consists of several bituminous overlays and new pavement on county roads across the county.
Detour:  There are no detours associated with this contract.  All work will be done under traffic.
Update:  11-6-20:  The 2020 Kandiyohi County Bituminous Program is now complete.  Final striping around Green Lake will occur next spring.  


#8 - CR 8 FDR (034-608-026)
Location:   CR 8 from CR 4 to CR 20 - MAP  
Contractor:   Duininck, Inc.
Approx. Start:   August 2019
Approx. Finish:   May 2020
Description:   This project consists of milling, reclamation, bituminous surfacing and Bridges 34J48 & 34J51
Detour:  MAP
Update:  7-31-20:  The project has been completed.


#15 - Mamre Township Bridge (034-599-039)
Location:   On 120th St NW approx. 1.2 miles south of CR 27 - MAP 
Contractor:   Riley Bros. Construction, Inc.
Approx. Start:   May 2020
Approx. Finish:   May 2020
Description:   This project consists of a bridge replacement in Mamre Township
Detour:  There is no detour associated with this project.  The road will be closed, use alternate routes.
Update:  6-19-20:  Project has been completed.